The application of the optimal sinter burden design in the sinter shop of No.1 Iron-making Plant in Tangshan Iron & Steel Corp was reported. By using burden calculation and simulating production under different situations, it is demonstrated that the technology can providethe relevant information in product quality and cost etc. for decision-makers. The technology has been used to guide production of the Sinter Shop since 2000, and a remarkable achievement has been obtained.
The application of the optimal sinter burden design in the sinter shop of No.1 Iron-making Plant in Tangshan Iron & Steel Corp was reported. By using burden calculation and simulating production under different situations, it is demonstrated that the technology can providethe relevant information in product quality and cost etc. for decision-makers. The technology has been used to guide production of the Sinter Shop since 2000, and a remarkable achievement has been obtained.