Meifeng Cai, Lan Qiao, Changhong Li, and Shuanghong Wang, Feasibility Study on Continuous Mining Method in Deep Position of Jinchuan Nickel Mine, China, J. Univ. Sci. Technol. Beijing, 8(2001), No. 2, pp. 81-85.
Cite this article as:
Meifeng Cai, Lan Qiao, Changhong Li, and Shuanghong Wang, Feasibility Study on Continuous Mining Method in Deep Position of Jinchuan Nickel Mine, China, J. Univ. Sci. Technol. Beijing, 8(2001), No. 2, pp. 81-85.
Meifeng Cai, Lan Qiao, Changhong Li, and Shuanghong Wang, Feasibility Study on Continuous Mining Method in Deep Position of Jinchuan Nickel Mine, China, J. Univ. Sci. Technol. Beijing, 8(2001), No. 2, pp. 81-85.
Citation:
Meifeng Cai, Lan Qiao, Changhong Li, and Shuanghong Wang, Feasibility Study on Continuous Mining Method in Deep Position of Jinchuan Nickel Mine, China, J. Univ. Sci. Technol. Beijing, 8(2001), No. 2, pp. 81-85.
Civil and Environmental Engineering School, University of Science and Technology Beijing, Beijing 100083, China
中文摘要
Jinchuan nickel mine is the largest nickel mine in China. Cut-and-fill mining method with high density cementing materials is used in the mine. The original mining design divided the mining operation into two steps. The first step stopped the mining rooms and the second step stopped the pillars. Because the two-step method made big trouble for finally mining pillars and strongly limited the mining speed and production, it was successfully changed to a continuous cut-and-fill method without pillars. However, the mining operation in the mine has been down to 800 m and the mining condition is getting worse and more complicated. Through systematical field investigations and 3-D FEM analysis, it is proved that the mining method without pillars is feasible for mining deeper orebodies in Jinchuan nickel mine.
Jinchuan nickel mine is the largest nickel mine in China. Cut-and-fill mining method with high density cementing materials is used in the mine. The original mining design divided the mining operation into two steps. The first step stopped the mining rooms and the second step stopped the pillars. Because the two-step method made big trouble for finally mining pillars and strongly limited the mining speed and production, it was successfully changed to a continuous cut-and-fill method without pillars. However, the mining operation in the mine has been down to 800 m and the mining condition is getting worse and more complicated. Through systematical field investigations and 3-D FEM analysis, it is proved that the mining method without pillars is feasible for mining deeper orebodies in Jinchuan nickel mine.